We want YOU to stay informed on where our construction is in your neighborhood, that's why we are posting construction updates for those of you wanting to know when YOU will get fiber. Our process has started with construction, once it is 100% complete we will move to installing your fiber.
Construction is on: N 1800th Ave, E 1800th Ave, Co Rd 00, 050N, 150N, 1700th Ave, E 1900th Ave, E 1650th
Majority of these roads have been plowed, boring is roughly 50% of the way done. Splicing is estimated to begin the week of March 23rd which would mean installs would start April 1st.
We are blowing fiber inside of our duct.
Come back daily for periodic updates.